"Stage of works" is an article that we publish periodically to keep you up to date with the activities on the Aqua City construction site. Block C1 is completed and Block C2 is being prep...
"The stage of the works" is an article that we publish periodically to keep you up to date with the activities on the Aqua City site, located in Giulesti, on 12-16 Rocilor Street. Block 1...
"The stage of the works" is a short article, published monthly, through which we communicate to the future Aqua City community the news from the construction site located on 12-16 Rocilo...
We publish a short monthly article in which we highlight the main works performed on the Aqua City site in the last 30 days. We have been doing this for 14 months already and you can fol...
We publish monthly information related to the progress of the works on the site of the Aqua City residential neighborhood, located in sector 6 of Bucharest, on the shores of Lake Morii a...
These are the last weeks in which we work simultaneously on two blocks - the first two blocks in the Aqua City residential neighborhood, designated the largest construction site in Buchar...
We are closely following the progress of the Aqua City site so that you are up to date with the evolution of this residential neighborhood that we are building north of Lake Morii. Now, w...
It's been 20 months since we worked on the Aqua City site and 10 months since we've kept a detailed track record of progress on the site. If you've been with us for the last few months -...
Our goal in the coming months: the completion, "in white", of block 1 in the Aqua City residential neighborhood. We follow, month by month, the way things are progressing on the site and ...
For about 2 months, the Aqua City team has been working on two blocks at the same time. The first 2 blocks out of a total of 6 of the residential neighborhood that rises north of Lake Mo...
It is March 31, 2021 and on the Aqua City site, two blocks are being worked on simultaneously! Block 1 has been completed on finishing. Block 2 is in the excavation stage of the foundati...
We are at the beginning of March and the Aqua City residential complex looks totally different from a year ago! The construction of the first block in Aqua City has been completed on the...
It's December and we've completed the structural part of the first block of the Aqua City residential project! Since the last status, published last month , the building has been raised ...
We are in the first part of November 2020 and the construction of the first block of the Aqua City residential project has reached the structure of the tenth floor out of the 11 provided...
It is October 19 and the construction of the first block of the Aqua City residential project has reached the structure of the ninth floor of the 11 provided. The sunset on Lake Morii is...
It is September 24 and the construction of the first block of the Aqua City residential project has reached the structure of the eighth fl...