11 months, 9 floors and over 150 subdivided apartments - or what is the status of the works at Aqua City

It is October 19 and the construction of the first block of the Aqua City residential project has reached the structure of the ninth floor of the 11 provided. The sunset on Lake Morii is getting better and better.

In the last month (September) the building has risen by 2 floors . Work is now underway on the structural part of the 9th floor, the last masonry parts of the fifth floor are being completed and work has begun on the interior, thermal, plumbing and electrical installations, reaching the 3rd floor. All processes will go in parallel, until the end of November 2020 , when we estimate that the structure part will be completed. The pouring of the screed for the protection of the thermal and electrical installations has started, the first 2 floors being already poured in the apartments.

In the meantime, we divided 150 apartments out of the 268 in Block no. 1

View here all types of new apartments available for sale.

All construction and finishing works are done by the general contractor, Multiconsult Adventure SRL , with an experience of over 10 years in the field .

For the execution of sanitary and thermal installations, we work with a team of 50 installers trained and certified by our partner, REHAU . Kits and mounting equipment are the same brand.

In fact, we use REHAU materials and services to:

  • drinking water installation - and we want to emphasize that each apartment in the 268 of Block 1 will benefit, in the kitchen, from 2 taps: on one will flow water from the public network, on the second alkaline water from the source that is located on the territory of the Aqua City ensemble , a source that has been known and exploited for four centuries
  • domestic water drainage system
  • centralized suction system
  • heating and cooling of surfaces

As a technical solution for joints, the RAUTITAN PEX-A pipe type was chosen, which has a proven lifespan of 50 years.

Why use the REHAU system for new Aqua City apartments?

  • high construction speed , even in cold weather
  • joint safety
  • permanent tightness
  • the joints are safe, compliant, of the highest quality , made without errors during assembly, due to the fact that it is a mechanical one
  • wide range of fittings - over 150
  • operational safety

What does this mean for you, the future tenant of the Aqua City residential complex?

  • the water in the public network will be of a high quality: tasteless, odorless, colorless
  • the life of the individual boiler will be longer - among other things, the REHAU system removes deposits from the installation
  • unpleasant surprises related to thermal installations will be a thing of the past

DID YOU KNOW THAT:

During the 11 months of construction of Block 1 in Aqua City, the following were used:

  • 1200 tons of iron
  • 11500 cubic meters of concrete.
  • 55000 YTONG bricks

For on-site visits - with protective equipment and a minimum distance of 250 m from the construction site - or for virtual visits , on WhatsApp - we invite you to first fill in the form here https://aquacity.ro/ro/noua- our house and our colleagues will contact you in maximum 24 hours.

Do you want to be as prepared as possible for the meeting? I have prepared for you on the blog: Top 10 questions to ask the developer when looking for an apartment. Part I