It is October 19 and the construction of the first block of the Aqua City residential project has reached the structure of the ninth floor of the 11 provided. The sunset on Lake Morii is getting better and better.
In the last month (September) the building has risen by 2 floors . Work is now underway on the structural part of the 9th floor, the last masonry parts of the fifth floor are being completed and work has begun on the interior, thermal, plumbing and electrical installations, reaching the 3rd floor. All processes will go in parallel, until the end of November 2020 , when we estimate that the structure part will be completed. The pouring of the screed for the protection of the thermal and electrical installations has started, the first 2 floors being already poured in the apartments.