The stage of the works at Aqua City - June 2021: we installed ceramic tiles, faience, doors and elevators

Our goal in the coming months: the completion, "in white", of block 1 in the Aqua City residential neighborhood.

We follow, month by month, the way things are progressing on the site and we regularly publish a status: what has been completed, what is being worked on, what is about to begin.

At this moment, at Block C1, we have completed:

At this moment, at Block C1, we have completed:

  • the masonry part;
  • compartmentalization of all apartments;
  • installation works of interior installations (thermal and electrical);
  • pouring screed for the protection of installations (thermal and electrical);
  • execution of fresh air intakes in apartments (on all stairs);
  • (on the side of electrical installations) cable beds for the columns of the apartments;
  • (on the side of electrical installations) the electrical supplies of the elevators;
  • the gas installations are 100% completed, both in the apartments and in the common spaces;
  • plastering the walls - the filling and finishing plasters are finished in all the apartments;
  • washable primer is completed on floors 1 - 10 (scale 1, 2,3);
  • installation of carpentry for windows and doors;
  • mounting glass for windows;
  • mounting the glass wall between the kitchen and the living room;
  • mounting the tiles on the hallways (and in the common spaces) reached the 10th floor (staircase 1), the 6th floor (staircase 2) and the 5th floor (staircase 3);
  • the installation of the tiles in the apartments was completed on floors 1 - 11 (scale 1), on floors 1 - 9 (scale 2) and on floors 1 - 10 (scale 3);
  • the installation of the tiles on the balconies of the apartments is 100% completed on the east facade and on the north facade;
  • waterproofing in bathrooms;
  • mounting the frames on the exterior doors in proportion of 100%;
  • installation of waterproofing on the terrace of the 3 stairs;

Regarding the utilities, common and private, we mounted:

  • one lift for each staircase;
  • radiators in all apartments (stairs 1, 2, 3);
  • thermal power plants - on scale 2 (floors 1, 3, 6);
News related to the facade of Block C1:

News related to the facade of Block C1:

  • On the north facade (towards the park) and on the east facade (towards Godeni), the decorative plaster was applied. The two facades are 100% completed.
  • On the south façade (towards the inner courtyard), the heating system is at the level of polystyrene cladding. Degree of completion: 50%
  • On the west façade (towards the inner courtyard), the thermal system at the level of the putty table was completed; the application of the decorative plaster follows. Degree of completion: 80%

Block C1, like the other blocks in the complex, was thought and designed so as to obtain the class A energy certificate. Part of this process means that the facades will have, mounted between floors, both expanded polystyrene and basalt wool with increased fire resistance. . Thermal insulation of facades will be done by mounting and diblation. The ultimate goal? To ensure excellent thermal and sound insulation.

At Block 1, we continue the works with:

At Block 1, we continue the works with:

  • washable primer on the 11th floor (scale 1, 2, 3);
  • washable layer (scale 1, 2, 3)
  • installation of tiles on the hallways (and in the common spaces), on floors 10 - 11 (staircase 1), floors 6 - 11 (staircase 2) and on floor 5 - 11 (staircase 3);
  • installation of tiles in apartments for floors 10 and 11 (scale 2, 3);
  • waterproofing in bathrooms, on the upper floors of the 3 stairs;
  • on the side of sanitary installations, the installation of water meters is performed
Work continues on the indoor park

Work continues on the indoor park

Located between block 1 and block 2 - where the parapets for the planted areas (planters) were poured in proportion of 40% and follows:

  • installation of waterproofing of planted areas
  • preparation of irrigation systems
  • filling with earth
  • plant population

Regarding the covered parking, the plots P1-P6 were fully executed. At the moment we are working on plots P7 and P8, where the resistance structure is 90% ready.

At Block C2, the works on the foundation continue: the building is leveled and the casings are mounted.

What does an Aqua City apartment look like?

Come to our showroom in 12-16 Rocilor Street to see a 2-room or 3-room apartment built to scale, fully furnished and equipped. There is also the possibility to go to the construction site and see one of the apartments 100% completed.

In both cases, there is a need for an appointment, which is done quickly and easily, here .